Tenant Information

Tenant Name: BINARY CONSULTING
Office Number: 409
Area: 47.03 m²
Floor: 4

Bill Information

Calculated According to: Invoice 40030262
Issued By: ELEKTROPRIVREDA SRBIJE
Period: April 2025
Generated: Jul 22, 2025 13:04

Consumption & Rate Information

15.00
Granted Power (kW)
282.34
Total Spent (kWh)
13.88 RSD
kWh Price

Calculation Breakdown

Description Calculation Amount
Fee for stimulus of privileged consumers 282.34 kWh × 0.816 230.39 RSD
Access to the system for distribution of electricity/Granted power 15.00 kW × 108.51 1,627.65 RSD
Access to the system for distribution of electricity/Active 282.34 kWh × 1.433 404.59 RSD
Consumed electricity 282.34 kWh × 13.88 3,918.88 RSD
Subtotal (before excise tax) Sum of items 1-4 6,181.51 RSD
Excise tax (7.5%) 6,181.51 RSD × 7.5% 463.61 RSD
TOTAL TO PAY Sum of all items 6,645.12 RSD

Rate Information

Privileged Consumer Rate
0.816
Distribution Access Rate
108.51
Distribution Active Rate
1.433
Excise Tax Rate
7.5%

Per-Meter Allocation for Tenant

Meter Meter Total (kWh) Tenant Allocation % Allocated to Tenant (kWh) Of Tenant Total
S-4.1
244.21 6.25% 15.26 5.41%
K-4.1
126.50 2.58% 3.26 1.16%
409
187.92 100.00% 187.92 66.56%
409-A
29.46 100.00% 29.46 10.43%
Total Allocated to Tenant 235.91 kWh = 100%

Note: Shown allocations reflect any custom period reduction, so their sum may differ from the bill's base meter allocations.

This bill was generated on July 22, 2025 p.m.31 13:04 by the Chinese Cultural Center Electricity Management System.

For questions about this bill, please contact the property management office.