Tenant Information

Tenant Name: BINARY CONSULTING
Office Number: 409
Area: 47.03 m²
Floor: 4

Bill Information

Calculated According to: Invoice 40995861
Issued By: ELEKTROPRIVREDA SRBIJE
Period: July 2025
Generated: Aug 26, 2025 12:37

Consumption & Rate Information

15.00
Granted Power (kW)
476.20
Total Spent (kWh)
14.12 RSD
kWh Price

Calculation Breakdown

Description Calculation Amount
Fee for stimulus of privileged consumers 476.20 kWh × 0.816 388.58 RSD
Access to the system for distribution of electricity/Granted power 15.00 kW × 108.51 1,627.65 RSD
Access to the system for distribution of electricity/Active 476.20 kWh × 1.433 682.39 RSD
Consumed electricity 476.20 kWh × 14.12 6,723.94 RSD
Subtotal (before excise tax) Sum of items 1-4 9,422.56 RSD
Excise tax (7.5%) 9,422.56 RSD × 7.5% 706.69 RSD
TOTAL TO PAY Sum of all items 10,129.25 RSD

Rate Information

Privileged Consumer Rate
0.816
Distribution Access Rate
108.51
Distribution Active Rate
1.433
Excise Tax Rate
7.5%

Per-Meter Allocation for Tenant

Meter Meter Total (kWh) Tenant Allocation % Allocated to Tenant (kWh) Of Tenant Total
S-4.1
2,113.50 6.25% 132.09 27.74%
K-4.1
1,449.45 2.58% 37.40 7.85%
409
286.07 100.00% 286.07 60.07%
409-A
20.64 100.00% 20.64 4.33%
Total Allocated to Tenant 476.20 kWh = 100%

Note: Shown allocations reflect any custom period reduction, so their sum may differ from the bill's base meter allocations.

This bill was generated on August 26, 2025 p.m.31 12:37 by the Chinese Cultural Center Electricity Management System.

For questions about this bill, please contact the property management office.