Tenant Information

Tenant Name: HIKVISION
Office Number: 502/503
Area: 379.94 m²
Floor: 5

Bill Information

Calculated According to: Standard calculation
Issued By: ELEKTROPRIVREDA SRBIJE
Period: November 2025
Generated: Dec 02, 2025 08:59

Consumption & Rate Information

30.00
Granted Power (kW)
1,686.85
Total Spent (kWh)
14.13 RSD
kWh Price

Calculation Breakdown

Description Calculation Amount
Fee for stimulus of privileged consumers 1,686.85 kWh × 0.816 1,376.47 RSD
Access to the system for distribution of electricity/Granted power 30.00 kW × 121.79 3,653.70 RSD
Access to the system for distribution of electricity/Active 1,686.85 kWh × 1.433 2,417.26 RSD
Consumed electricity 1,686.85 kWh × 14.13 23,835.19 RSD
Subtotal (before excise tax) Sum of items 1-4 31,282.62 RSD
Excise tax (7.5%) 31,282.62 RSD × 7.5% 2,346.20 RSD
TOTAL TO PAY Sum of all items 33,628.82 RSD

Rate Information

Privileged Consumer Rate
0.816
Distribution Access Rate
121.79
Distribution Active Rate
1.433
Excise Tax Rate
7.5%

Per-Meter Allocation for Tenant

Meter Meter Total (kWh) Tenant Allocation % Allocated to Tenant (kWh) Of Tenant Total
S-6.3
1,895.58 66.66% 1,263.59 74.91%
K-5.1
618.65 28.97% 179.22 10.62%
P2/DB-5F-2
22.95 100.00% 22.95 1.36%
P3/DB-5F-3
0.92 100.00% 0.92 0.05%
P2/DBA-5F-2
132.90 100.00% 132.90 7.88%
P3/DBA-5F-3
87.27 100.00% 87.27 5.17%
Total Allocated to Tenant 1,686.86 kWh = 100%

Note: Shown allocations reflect any custom period reduction, so their sum may differ from the bill's base meter allocations.

This bill was generated on December 02, 2025 a.m.31 08:59 by the Chinese Cultural Center Electricity Management System.