Tenant Information

Tenant Name: HAINAN AIRLINES
Office Number: 719
Area: 37.56 m²
Floor: 7

Bill Information

Calculated According to: Standard calculation
Issued By: ELEKTROPRIVREDA SRBIJE
Period: November 2025
Generated: Dec 23, 2025 10:06

Consumption & Rate Information

10.00
Granted Power (kW)
239.36
Total Spent (kWh)
14.15 RSD
kWh Price

Calculation Breakdown

Description Calculation Amount
Fee for stimulus of privileged consumers 239.36 kWh × 0.816 195.32 RSD
Access to the system for distribution of electricity/Granted power 10.00 kW × 121.79 1,217.90 RSD
Access to the system for distribution of electricity/Active 239.36 kWh × 1.666 398.77 RSD
Consumed electricity 239.36 kWh × 14.15 3,386.94 RSD
Subtotal (before excise tax) Sum of items 1-4 5,198.93 RSD
Excise tax (7.5%) 5,198.93 RSD × 7.5% 389.92 RSD
TOTAL TO PAY Sum of all items 5,588.85 RSD

Rate Information

Privileged Consumer Rate
0.816
Distribution Access Rate
121.79
Distribution Active Rate
1.666
Excise Tax Rate
7.5%

Per-Meter Allocation for Tenant

Meter Meter Total (kWh) Tenant Allocation % Allocated to Tenant (kWh) Of Tenant Total
S-7.1
4,696.00 4.34% 203.81 85.15%
K-6.1
831.54 2.00% 16.63 6.95%
P3/DB-7F-3
128.37 11.26% 14.45 6.04%
P3/DBA-7F-3
39.72 11.26% 4.47 1.87%
Total Allocated to Tenant 239.36 kWh = 100%

Note: Shown allocations reflect any custom period reduction, so their sum may differ from the bill's base meter allocations.

This bill was generated on December 23, 2025 a.m.31 10:06 by the Chinese Cultural Center Electricity Management System.