Tenant Information

Tenant Name: CSCOD
Office Number: 507
Area: 135.42 m²
Floor: 5

Bill Information

Calculated According to: Standard calculation
Issued By: ELEKTROPRIVREDA SRBIJE
Period: December 2025
Generated: Jan 08, 2026 11:25

Consumption & Rate Information

30.00
Granted Power (kW)
1,081.65
Total Spent (kWh)
14.15 RSD
kWh Price

Calculation Breakdown

Description Calculation Amount
Fee for stimulus of privileged consumers 1,081.65 kWh × 0.816 882.63 RSD
Access to the system for distribution of electricity/Granted power 30.00 kW × 121.79 3,653.70 RSD
Access to the system for distribution of electricity/Active 1,081.65 kWh × 1.666 1,802.03 RSD
Consumed electricity 1,081.65 kWh × 14.15 15,305.35 RSD
Subtotal (before excise tax) Sum of items 1-4 21,643.71 RSD
Excise tax (7.5%) 21,643.71 RSD × 7.5% 1,623.28 RSD
TOTAL TO PAY Sum of all items 23,266.99 RSD

Rate Information

Privileged Consumer Rate
0.816
Distribution Access Rate
121.79
Distribution Active Rate
1.666
Excise Tax Rate
7.5%

Per-Meter Allocation for Tenant

Meter Meter Total (kWh) Tenant Allocation % Allocated to Tenant (kWh) Of Tenant Total
S-5.1
3,336.50 18.75% 625.59 57.84%
K-5.1
1,106.37 10.32% 114.18 10.56%
507
181.10 100.00% 181.10 16.74%
507-A
160.78 100.00% 160.78 14.86%
Total Allocated to Tenant 1,081.65 kWh = 100%

Note: Shown allocations reflect any custom period reduction, so their sum may differ from the bill's base meter allocations.

This bill was generated on January 08, 2026 a.m.31 11:25 by the Chinese Cultural Center Electricity Management System.