Tenant Information

Tenant Name: JING GONG
Office Number: 605
Area: 225.14 m²
Floor: 6

Bill Information

Calculated According to: Standard calculation
Issued By: ELEKTROPRIVREDA SRBIJE
Period: April 2026
Generated: May 06, 2026 14:24

Consumption & Rate Information

30.00
Granted Power (kW)
396.81
Total Spent (kWh)
14.15 RSD
kWh Price

Calculation Breakdown

Description Calculation Amount
Fee for stimulus of privileged consumers 396.81 kWh × 0.816 323.80 RSD
Access to the system for distribution of electricity/Granted power 30.00 kW × 121.79 3,653.70 RSD
Access to the system for distribution of electricity/Active 396.81 kWh × 1.666 661.09 RSD
Consumed electricity 396.81 kWh × 14.15 5,614.86 RSD
Subtotal (before excise tax) Sum of items 1-4 10,253.45 RSD
Excise tax (7.5%) 10,253.45 RSD × 7.5% 769.01 RSD
TOTAL TO PAY Sum of all items 11,022.46 RSD

Rate Information

Privileged Consumer Rate
0.816
Distribution Access Rate
121.79
Distribution Active Rate
1.666
Excise Tax Rate
7.5%

Per-Meter Allocation for Tenant

Meter Meter Total (kWh) Tenant Allocation % Allocated to Tenant (kWh) Of Tenant Total
S-6.1
597.22 26.08% 155.75 39.25%
K-6.1
1,348.15 11.25% 151.67 38.22%
P1/DBA-6F-1
378.20 22.51% 85.13 21.45%
P1/DB-6F-1
18.93 22.51% 4.26 1.07%
Total Allocated to Tenant 396.82 kWh = 100%

Note: Shown allocations reflect any custom period reduction, so their sum may differ from the bill's base meter allocations.

This bill was generated on May 06, 2026 p.m.31 14:24 by the Chinese Cultural Center Electricity Management System.

For questions about this bill, please contact the property management office.